Question Description

BZ460Project Management

Directions:Be sure to make an electronic copy of your answer before submittingit to Ashworth College for grading. Unless otherwise stated, answer incomplete sentences, and be sure to use correct English spelling andgrammar. Sources must be cited in APA format. Refer to the”Assignment Format” page for specific format requirements.

Calculate the ES, EF, LS, and LF times and the slack foreach activity in the figure below and identify the critical path for theproject. Can the project be completed in 40 weeks? Assume that Activity Aactually finished at 3 weeks, Activity B actually finished at 12 weeks, andActivity C actually finished at 13 weeks. Recalculate the expected projectcompletion time. Which activities would you focus on in order to get the projectback on schedule?